Carpenter A can build a fence in 10 days. Carpenter B can build the same fence in 15 days. Carpenter A and Carpenter B build the fence together but experience a 2-day delay due to bad weather. Let be the total time, in days, required for them to complete the job working together, including the delay. Which of the following equations is satisfied by ?