A factory uses two types of raw materials, Material P and Material Q, to produce two different products, Product X and Product Y. Each unit of Product X requires 4.5 pounds of Material P and 2 pounds of Material Q. Each unit of Product Y requires 3 pounds of Material P and 5 pounds of Material Q. The factory has a daily supply of 450 pounds of Material P and 300 pounds of Material Q. If is the number of units of Product X and is the number of units of Product Y produced daily, the production is constrained by the inequalities:
(for Material P)
(for Material Q)
If the factory produces 60 units of Product X in a day, what is the maximum number of units of Product Y that can be produced, given the constraints?